Solel Boneh asked for permission to alter the plan because the original plan was unsuitable and was not economically viable.
The Jerusalem District Court has permitted Solel Boneh Building and Infrastructure (TASE:SOLB) to build the second stage of a residential neighborhood in the Har Homa area of Jerusalem. The court approved the plan, even though the new construction contravenes the original plan, and even though some of the apartments have already been sold. Solel Boneh asked for permission to alter the plan because the original plan by D. Rothstein Construction and Properties could not be implemented, was unsuitable to the conditions, did not take into account the security situation and its effect on the lack of personnel, and was not economically viable.
Solel Boneh said that even in the first stage of the plan, it became clear that construction costs were extremely high, far beyond the preliminary estimate, and had caused the company heavy losses. Sol Boneh notified the court that forcing it to carry out the Har Homa residential project according to the original plan would cause it huge losses, and force it to return the land to the Israel Land Administration (ILA).
Jerusalem District Court Judge Orit Efaal-Gabay ruled that Solel Boneh could not be forced to carry out construction according to the original plan. She said there were two possibilities, “each worse than the other.” Either Solel Boneh would have to freeze the second stage, or it would have to call off the project, and return the land to the ILA. Efaal-Gabay ruled that the costs of these were too high.
Published by Globes [online] - www.globes.co.il - on February 1, 2004