Metro dispute over station entrances to delay tenders

Metro credit: Bar Lavi
Metro credit: Bar Lavi

NTA believes stations only need one entrance while the Israel Planning Administration says several are necessary.

The Metro, Israel's biggest-ever national project, requires huge capital and adherence to schedules to build an underground railway network spanning 24 local authorities in the Tel Aviv metropolitan region, with over 100 stations. Now, a dispute over the number of entrances and exits at stations could delay the project.

The three Metro lines are scheduled to begin operating gradually between 2034 and 2040. According to the presentation by the NTA Metropolitan Mass Transit System made to contractors last December, in 2025 NTA will begin expropriating land and property and start readying land and clearing infrastructure in preparation for the start of excavations, and will engage in acoustic shielding of residential apartments adjacent to the work centers.

In 2026, NTA is due to publish the tenders for the Infra 1 phase, which includes digging tunnels and stations, and a year later it is due to publish tenders for the the Infra 2 phase, which includes installation of systems, ordering equipment and trial runs. In 2028, according to the schedule, excavation work in the field will begin.

However, there is concern that tenders due to be published next year will be delayed. This is because the Israel Planning Administration set that there will be 2-5 exits from each Metro station, but NTA interpreted this as a maximum guideline, and has planned one exit at many stations. The issue was brought to the National Infrastructure Committee, which was surprised to see NTA's planning, and ordered it to re-plan a large part of the stations again, so that there would be more exits and entrances from them, except where there is an engineering problem to do so.

NTA believes that a single exit will lead to more efficient passage flow, with left complications underground and less damage to urban life above ground. The Israel Planning Administration refuses to accept this approach. As part of the statutory planning, many stations had multiple entrances and exits, with the intention of expanding the positive impact of metro stations on the urban environment. Industry sources call the planning a sham, while others play it down as a professional dispute.

Many more challenges

In any case, the detailed planning stages of the three lines are just one challenge among many that could affect the project's schedules and lead to delays. The Metro Law, which was passed after great delay, is supposed to create planning certainty for the project, give it priority and remove regulations, but from experience gained in previous projects, the lack of coordination between government agencies - and certainly with those outside it, such as communications companies - creates gaps in planning and budget estimates, as well as In the timetables.

The Ministries of Finance and Transport have also struggled for over two years to agree on a director of the Metro Authority - the government body appointed to remove obstacles for the project, which has therefore not yet been established. Only next month will a new search committee convene for the director of the authority, after the previous process that dragged on for years saw the leading candidates withdraw from the race.

In addition, according to the plan, NTA will have to clear 40 million cubic meters of excess landfill from the city center, and build an independent power plant to supply electricity to the Metro. NTA will have to hire a huge number of foreign engineers and workers, while Israel remains an unattractive destination due to the war. It will have to build a huge logistics centers, as well as encourage Israeli factories to produce segments in the form of arched concrete slabs to line the tunnels, from which it will require1.25 million units.

In parallel with having to build the underground transport system, which will carry two million passengers a day, the financing model is being established. Alongside 50% funding from the state budget, 25% will also come from metropolitan funding through taxation and 25% from value enhancement as a result of real estate improvements that will need to grow in tandem with the construction of the project. The NTA will need to encourage, and perhaps establish, a real estate management company that will handle construction above the stations, train depots and transport hubs that will be built.

Mitigation of consequences of the war

The estimated annual economic benefit from the Metro is NIS 25-30 billion, and these are attributed to improved travel times, savings on vehicle maintenance and parking, and broader implications such as densification between business centers, which creates efficiency, land savings and urban improvement.

From the material transferred to the contractors, it appears that the Ministry of Finance sees the project as one of the tools for mitigating the heavy economic consequences of the war, which include an increase of NIS 195 billion in the 2023-2024 deficit, alongside a steady increase of NIS 20 billion in the defense budget and a negative growth forecast.

The Israel Planning Administration said, "The Administration is working in cooperation with the NTA to ensure optimal planning of the Metro stations, so that the stations that are built to enable the best service for passengers. As part of this, coordination meetings are held between the Planning Administration and the NTA, in which all aspects of each station are examined."

NTA said, "As in any planning process, and certainly as complex as planning the Metro network, several rounds of mitigation are held between the Israel Planning Administration and the planning director, and the same is true regarding the number of entrances in stations. The discussions are held in full cooperation, with the aim of optimizing and streamlining the service for passengers."

Published by Globes, Israel business news - en.globes.co.il - on February 24, 2025.

© Copyright of Globes Publisher Itonut (1983) Ltd., 2025.

Metro credit: Bar Lavi
Metro credit: Bar Lavi
Fencing goes up Petah Tikva's Segula neighborhood  credit: NTA The Metro is really happening

Although there are skeptics who doubt that the project will ever be realized, there are now enough signs on the ground to indicate that they are probably wrong.

Ben Gurion airport Terminal 1 credit: Shutterstock Ben Gurion airport's Terminal 1 reopens

Terminal 1 at Ben Gurion airport reopened yesterday to domestic flights, while international flights will start using the terminal from Sunday, March 30.

Minister of Interior Moshe Arbel credit: Cadya Levy Interior Minister: There is no deep state in Israel

Minister of Interior Moshe Arbel told the Globes Services conference that civil servants are dedicated employees who serve the public.

Minimum wage credit: Tali Bogdanovsky Minimum wage in Israel to rise next week

The monthly minimum wage in Israel will be revised upwards by 6%.

Bank of Israel  credit: Shutterstock/Alon Adika Bank of Israel slams gov't fiscal policy

Governor Prof. Amir Yaron wrote in the annual report that the government's measures are not enough to ensure a sustained decline in debt-to-GDP ratio.

Minister of Justice Yariv Levin credit: Noam Moskovitz Knesset Spokesperson Knesset passes Judicial Selection Law

The new law makes judicial appointments subject to political control.

Airbnb credit: Reuters Knesset ignores Airbnb tax evasion loophole

The Israel Hotels Association has slammed the government's indifference to tax evasion by Airbnb landlords, which it insists promotes unfair competition.

GMT CFO Eran Tibon credit: PR Political tensions tempt Israelis to move funds abroad

According to data from advanced financial services company Global Money Transfer, steps taken by the Israeli cabinet to oust Shin Bet chief Ronen Bar, and Attorney General Gali Baharav-Miara, could cause capital to flee Israel.

Sde Dov credit: Guy Yehieli Tenders close for 2,744 more homes in Sde Dov

Four tenders closed last month for the north Tel Aviv district saw a decrease of about 40% in the prices of land, and there is great interest in the prices these latest tenders will fetch.

Rafael CEO Yoav Turgeman credit: Rafael Spokesperson Rafael CEO: Iron Beam will be ready in 2025 as promised

In presenting record financial results for 2024, Yoav Turgeman tells "Globes" that the high energy laser weapon system will be operational this year.

Tel Aviv credit: Shutterstock Rent rises moderate due to emigration and reserve duty

Rents only rose 4% in 2024, the Bank of Israel reports, despite the large number of evacuees, due to the negative migration balance and the large number of young people in the army reserves.

Moody's, Benjamin Netanyahu, Bezalel Smotrich, credit: Shutter stock, Government Spokesperson, Tali Bogdanovsky Moody's: Political risks weigh on Israel's rating

"Israel's sovereign credit profile reflects very high political risks that have weakened economic and fiscal strength."

Stef Wertheimer  credit: Reuters Industrialist and philanthropist Stef Wertheimer dies aged 98

Wertheimer founded Iscar, which was sold to Warren Buffett's Berkshire Hathaway, and was behind many industrial and social initiatives, as well as having a brief political career.

Island founders Dan Amiga and Mike Fey credit: Antonio Delucci Browser security co Island raises $250m at $5b valuation

The company has developed a communications technology that enables fast remote connection to corporate computers.

Yossi and Shlomi Amir  credit: Jonathan Bloom Shufersal doubles annual profit

Streamlining measures by brothers Yossi and Shlomi Amir since they took control have vastly improved the supermarket chains profitability metrics.

Africa Israel Residence CEO Ronit Eshed Levy credit: Cadya Levy "Jewish communities want to move together to Jerusalem"

Africa Israel Residence CEO Ronit Eshed Levy told the Globes Going Long on Israel investment conference about urban renewal in Jerusalem.

Twitter Facebook Linkedin RSS Newsletters גלובס Israel Business Conference 2018